I suspect they are going with the low charge rate to lower install costs. You *might* be able to install 4 50kw posts on the existing service. It’s very unlikely that a gas station has 4x150kW = 600kw/750KvA sitting idle, as that is more than a whole station would use. The additional cost and hassle of bringing in new…